Downtown Outdoor Dining Program

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

The Downtown Outdoor Dining launched on August 15, 2024, and is overseen by the Economic Development department in the City Manager's Office.  Businesses fronting G Street between 2nd and 3rd Streets have been able to rent space on the platforms since December 2024. This applies to local restaurants who are requesting to either construct an expanded service area in specific parts of the public right-of-way or utilize existing public civic space for expanded service.  

By July 1, 2026, all of downtown Davis businesses that have outdoor dining should be in compliance of the Outdoor Dining program. The Outdoor Dining program is starting with G Street as it is newly renovated with the platforms. 

There is no deadline to apply for the Downtown Outdoor Dining Program. Businesses can submit forms anytime during business hours for the Downtown Outdoor Dining Program. 

If you're interested in learning about the G Street Activation page, click here.

STEP 1: Interest Form
STEP 2: License Agreement Application
STEP 3: License Agreement Execution
Ongoing Renewals/Conversion of Existing Agreements

TIMELINE

Below is a timeline of milestones for the project. Please note that dates in the future may change.

Click here for the 9/4/24 video of the outdoor dining program on G Street presentation that provides an explanation to the schedule below (please note that a few of the dates in the video have since been updated).

  • 8/15/24: Outdoor Dining Interest Form released
  • 9/4/24: Downtown Outdoor Dining Program/G Street presentation (updated 9/27/24). Click for the meeting video
  • 9/12/24: Proposed Fee Schedule shared with the DDBA Board (Updated on 9/27/24)
  • 9/13/24: Draft Checklist and Application for the Outdoor Dining Program License Agreement released. Submit comments by 10/4/24 to outdoordining@cityofdavis.org
  • 9/16/24: Construction Notice to Proceed is issued
  • 9/17/24: Road closure resolution that was brought to, and passed by, the City Council
  • 9/18/24: Municipal Code update brought to the Recreation and Parks Commission
  • 9/25/24: Municipal Code update brought to the Planning Commission
  • 10/15/24: Furnishing and Design Standard, Municipal Code updates and Fee Schedule brought to the City Council
  • 11/12/24: Municipal Code updates brought again to the City Council
  • December 2024: Estimated date of completion for construction of the platforms
  • 12/10/24: License agreement application and checklist posted.
  • 12/12/24: The City can enter into license agreement when the street closure ordinance goes into effect. 
  • January 2025: Downtown Streets Team contract renewal
  • 2/5/25: Q&A session with businesses regarding the Downtown Outdoor Dining Program
  • 1/30/26: Operations and Maintenance Baseline Yearly Budget is completed
  • 7/1/26: Compliance deadline for existing businesses with the Downtown Outdoor Dining Program