Aspen Greenbelt/Covell Blvd Path Update 10/29/24

Post Date:October 29, 2024 10:45 am

Aspen Greenbelt/Covell Blvd Path Update 10/29/24

Phase 1 and 2 – Aspen Greenbelt Path below Bryce Lane and Saratoga Lane – ALMOST COMPLETE! The path in this section is open! Most of the work is complete except for some patch paving that will occur at a later date, closing the path again for a day or two. The City will update the public on patch paving dates. All entrance/exit ramps to this path section will be open by 10/30.  

Phase 3 and 4 - Aspen Greenbelt Path including Bryce Lane/Saratoga Lane intersections and above to Glacier Drive crossing Olympic DriveThis path section is now closed for paving and concrete ramp construction at path entrances through approximately Nov. 18. After paving is complete in this phase, the path will be open for travel, but all path entrances/exits may not be open due to continuing concrete work. The City will update the public when the paving is complete and when the path entrances/exits are open.

Path users will need to detour to Denali Dr, Olympic Dr or to the Evergreen Greenbelt (parallel to El Capitan St).

Upcoming Work:

Phase 5 – Covell Blvd multi-use path from Shasta Drive to Denali Drive

Work will commence in mid-November for about two weeks for paving and concrete ramp construction at path entrances/exits through early December.

Phase 6 – Covell Blvd multi-use path from Denali Drive to just after UC Davis Medical Group business office at 2660 West Covell

Work will commence in early December for about two weeks for paving with concrete ramp construction at path entrances through mid-December.

Please stay tuned for further schedule updates. As always, this schedule is weather dependent.

Please contact City of Davis Public Information Officer Barbara Archer with questions at barcher@cityofdavis.org.

 